Request
Please provide any existing modelling, calculations or reports showing how much heat and electricity the new Edmonton Energy Recovery Facility is expected to produce at different levels of residual-waste throughput.
In particular, please provide any information showing:
- heat and electricity output under each of the waste scenarios A–E used in the North London Joint Waste Strategy, for each year or modelled year for which figures are held, including the amount of heat available and the number of homes that could receive heating and hot water; and
- the assumptions used to convert heat output into numbers of homes.
If NLWA has not modelled this relationship, please confirm that no such information is held.
Response
Good afternoon,
Further to our acknowledgement of your environmental information request with reference (2026-290), our response is as follows.
Your request
Please provide any existing modelling, calculations or reports showing how much heat and electricity the new Edmonton Energy Recovery Facility is expected to produce at different levels of residual-waste throughput.
In particular, please provide any information showing:
- heat and electricity output under each of the waste scenarios A–E used in the North London Joint Waste Strategy, for each year or modelled year for which figures are held, including the amount of heat available and the number of homes that could receive heating and hot water; and
- the assumptions used to convert heat output into numbers of homes.
If NLWA has not modelled this relationship, please confirm that no such information is held.
Our response:
NLWA does not hold any modelling showing heat and electricity output against Joint Waste Strategy scenarios A-E. The only modelling held is that contained within the Combined Heat and Power (CHP) Development Strategy and associated Energy Recovery Facility (ERF) design documentation, which is publicly available on the North London Heat and Power Project website:
https://northlondonheatandpower.london/media/r04i55j2/ad05-06_chp_development_strategy_lores.pdf
The modelling contained within these documents is based on the design operation of the facility rather than the waste scenarios used within the North London Joint Waste Strategy. The new Energy Recovery Facility has been designed with a nominal throughput of up to 700,000 tonnes of waste per annum and a processing capacity of up to 88 tonnes per hour.
The facility has also been designed to operate efficiently across a range of throughput levels. The existing Edmonton EcoPark energy from waste plant does not have sufficient capacity for all residual household waste arising within north London. The new facility has a capacity for 700,000 tonnes but can operate at lower throughputs, including around 490,000 tonnes per annum. This flexibility enables the facility to respond to variations in waste arisings over time, including potential reductions resulting from increased waste prevention, reuse and recycling, as well as higher waste volumes should they arise.
The Joint Waste Strategy projections to 2050 indicate that, with the exception of Scenarios A and E, projected household residual waste arisings broadly fall within the facility's operational range of approximately 490,000 to 700,000 tonnes per annum. In summary scenario A is a "high growth" waste scenario and scenario E envisages full achievement of the Mayor of London's highly demanding recycling targets. Both are modelled in the Joint Waste Strategy for the sake of completeness. Scenario A is not an outcome that boroughs seek to achieve. As can be seen from the graphs in the Joint Waste Strategy appendices, scenario E is a major departure from current trends, and it would be unwise to plan infrastructure on the basis that this will be certain to be achieved.
NLWA does not hold separate modelling which translates those scenario forecasts into projected heat or electricity outputs for each individual throughput level. Electricity generation figures beyond those contained within the published CHP Development Strategy and associated design documentation are therefore not held.
It should also be noted that hundreds of thousands of tonnes of residual waste generated in north London by businesses are currently sent to private sector facilities outside of north London, leading to increased transport emissions. It is likely that some of this waste is exported. If there were to be additional capacity in the new plant, it would enable north London's residual commercial waste to be treated closer to source, leading to better environmental outcomes.
NLWA does not hold any modelling or assumptions used to convert thermal heat output into an estimated number of homes supplied. This information is held by Energetik, which is responsible for the distribution of heat from the Energy Recovery Facility via its Energy Centre in Edmonton. The Energy Recovery Facility is designed to export up to 60MWth of thermal heat; however, assumptions regarding how this output translates into the number of homes that could receive heating and hot water are not held by NLWA for the purposes of the Freedom of Information Act. Requests for this information should therefore be directed to Energetik.
If you are dissatisfied with the handling of your request, you may ask for an internal review, which should be submitted within two months of when you received our response to either informationrequests@nlwa.gov.uk or enquiry form quoting the above reference.
If you are not content with the outcome of the review, you may complain to the Information Commissioner, Wycliffe House, Water Lane, Wilmslow, Cheshire, SK9 5AF, or via their online portal. The Information Commissioner will not usually accept complaints before a review has been completed.
Website: https://ico.org.uk
Kind Regards,
North London Waste Authority